IterationPlan

Jim'sPages => StoryProcess => IterationPlan

A top level iteration plan shows the number of iterations expected.  This picture suggests how iterations overlap, though the relative scale of each activity is not precise.  This kind of iteration keeps the development team the most consistently occupied.  Planning and deployment are more bursty.

Plan Analyze, Design Construct Deploy
Plan Analyze, Design Construct Deploy
Plan Analyze, Design Construct Deploy

At a lower level of detail, we can show exactly which stories are expected in each plan.  A Microsoft Project plan might roll up to look much like the figure above, but expand into stories for each iteration.  I would not encourage the master plan to expand into tasks for each story, but sub-plans belonging to programming teams might.

Iteration Plan Summary

Following is one format for an iteration plan summary.  It focuses on planning the work yet to be done and shows changes to the plan over time.

Before each iteration we hold a PlanningGame for all remaining iterations. The cells under a date represent the plan as of the start of the iteration. The Stories and Points columns show the planned work for each iteration.  The points represent a predicted velocity.  The Total line shows all work remaining to be done. 

 As Of Date 07/01
Plan
07/15
Plan
07/29
Plan
08/12
Plan
10/04
Plan
  Start of 1 Start of 2 Start of 3 Start of 4 Total
Iteration Stories Points Stories Points Stories Points Stories Points Stories Points
1 8 40 6 30            
2 9 42 10 45 10 45        
3 8 39 9 46 10 50 9 45    
4 7 41 7 41 8 45 9 50 8 45
Release
Remaining
32 162 26 132 18 95 9 50 0 0
Future
Remaining
0 0 0 0 1 5 1 5 2 10

At the end of each iteration we show actual stories and points completed in the green cells.  Points completed equals the actual velocity!  Any stories not completed and any new stories are moved into the remaining iterations, or completely out of the release and into "future".

See how this plan worked out.

What if the customer had added the three stories in I3 planning but had not allowed any to drop into future? Customers and managers are not allowed to force velocity beyond the programmer estimates, so the only solution would have been to add another iteration. 

An iteration is like a child's wooden box of blocks. You can only fit so many blocks in the box. The box won't stretch to hold more just because you really, really want it to.

Project Size summary

Here's an interesting row that could be added to the chart above. This shows the actual for all completed iterations plus planned for remaining iterations, or the total size of the project. It shows some growth in customer desires, but in the end, not much growth in actual delivery. Did the manager cave in to a persuasive customer instead of listening to the programmers' estimates?

07/01
Plan
07/15
Plan
07/29
Plan
08/12
Plan
10/04
Plan
Start of 1 Start of 2 Start of 3 Start of 4 Total
Stories Points Stories Points Stories Points Stories Points Stories Points
32 162 32 162 34 170 34 170 33 165

Iteration Progress Summary

This chart focuses on accomplishments. It illustrates that we were a little generous with our predicted velocity as three iterations out of four did not deliver all the planned stories. Actual velocity was pretty steady after taking one iteration to get up to speed. Would you get an actual of 45 and promise 50 more than once?

Iteration

Plan

Actual

Deviation

Stories Points Stories Points Stories Points

I1

8

40

6

30

-2

-10

I2

10

45

10

45

0

0

I3

10

50

9

45

-1

-5

I4

9

50

8

45

-1

-5

Total

 

 

33

165

-4

-20